The Planning Inspectorate

Appeals & Other Casework


Planning Appeals
Enforcement Appeals
Common Land
Highways and Transport
Local Development Frameworks
Regional Spatial Strategy
Rights of Way
All types of Appeal / Casework
General Information

Complaints

Employment
FAQS
Forms
Freedom of Information
Newsletter
Press Releases and Notices
Publications
Related sites
Site Help
Statistics
Targets
Who's Who

Site Settings

You are currently viewing information for England.

View information for Wales

Language options:

View this site in Welsh

Modified: 11-Mar-2009

Advice Produced by The Department for Communities and Local Government

Demonstrating a 5 Year Supply of Deliverable Sites

Background

1. PPS3 requires Local Planning Authorities from 1 April 2007  to assess and demonstrate the extent to which existing plans already fulfil the requirement to identify and maintain a rolling 5-year supply of deliverable land for housing (paragraph 7) as this influences how planning applications are determined (see PPS3 paragraphs 68-73).

2. In particular, PPS3 paragraph 71 states that 'where Local Planning Authorities cannot demonstrate an up to date 5-year supply of deliverable sites……., they should consider favourably planning applications for housing, having regard to the policies in this PPS including the considerations in paragraph 69'.

3. It follows that where an LPA can demonstrate a 5-year supply of deliverable sites then they should consider planning applications having regard to PPS3, existing Development Plan policies as well as other material considerations.

Purpose

4. This paper sets out advice to Government Offices and the Planning Inspectorate in considering whether Local Planning Authorities are able to demonstrate a 5-year supply of specific sites which are deliverable in the terms of paragraph 54 of PPS3.  This applies both to initial assessments as well as those carried out as the 5-year land supply is regularly reviewed and rolled forward, as required by PPS3.  

Approach

5. There are three main stages:

i)    Identify the level of housing provision to be delivered over the following 5 years which, in the first instance, will be from 1st April 2007 to end March 2012.  Local Planning Authorities should use, where available, housing provision figures in adopted Development Plans, adjusted to reflect the level of housing that has already been delivered (within the lifetime of the current plan).  Where housing provision figures are not available in the Development Plan for the following 5 years, Local Planning Authorities should make the best available estimate of the level of housing required over the full 5-year period.  For example, this may include having regard to the evidence underpinning housing provision policies in the emerging Regional Spatial Strategy, projecting forward based upon current Development Plan figures or drawing on other relevant and up-to-date information.

ii)   Identify sites that have the potential to deliver housing during the following 5 years. Potential sites include those that are allocated for housing in the Development Plan, sites that have planning permission (outline or a full planning permission that has not been implemented) and specific, unallocated brownfield sites that have the potential to make a significant contribution to housing delivery during the 5 year period. Such unallocated brownfield sites would normally have been identified by the Local Planning Authority as being suitable for a housing use and have made sufficient progress through the planning process at the time of the assessment to be able to be considered deliverable in the terms of paragraph 54 of PPS3.    

iii) Assess the deliverability of the identified potential sites. Paragraph 54 of PPS3 says that to be deliverable, sites should:

Assessing Deliverability

6.    Local Planning Authorities will need to assess whether potential sites (see paragraph 5 ii) are deliverable in the terms of paragraph 54 of PPS3, drawing upon up-to-date information and ensuring that their judgements are clearly and transparently set out, noting any assumptions made.  It is important that developers and local communities understand the basis on which the assessment is made.

Deliverability Criteria

Assessing Deliverability

Available

Does the information that supports either the allocation of a site in an up-to-date plan (subject to planning permission), or the granting of a planning permission, clearly indicate that site is available now?
If existing information is not sufficient, it may be necessary for the Local Planning Authority to gather further, up-to-date evidence by discussing availability of the site with relevant developers/landowners.

Suitable

Can sites that are allocated or have planning permission be regarded as being suitable?
This will usually be a reasonable assumption, but it may be necessary to assess whether circumstances have changed (e.g. since a site was allocated) that would alter the suitability of the site for housing.    

Achievable

Does the information supporting the site allocation or planning permission clearly demonstrate that there is a reasonable prospect of housing being delivered within 5 years?  It may be necessary to discuss with relevant developers/ landowners and/or analyse current housing market conditions in order to make an informed judgement about this.

8.   Unallocated brownfield sites may be included in the 5 year supply of deliverable sites, but only where the Local Planning Authority is satisfied, having considered the particular circumstances of the specific site, that the site will meet all the tests of deliverability in paragraph 54 of PPS3 and will make a significant contribution to the delivery of housing during the relevant 5 year period.  As indicated above, such unallocated brownfield sites would normally have made sufficient progress through the planning process to be able to be considered deliverable in the terms of paragraph 54 of PPS3. 

9.   Unallocated sites that are not likely to make a significant contribution to the delivery of housing during the relevant 5-year period should not be taken into account in an assessment of the 5-year supply until a planning permission has been granted and the land supply is being reviewed.

Consequences of the Assessment