Planning Inspectorate Newsletter - Issue 4

The Planning Inspectorate Recovery PlanPhoto of Phil Hammond

The Planning Inspectorate is committed to achieving all its performance targets during this financial year.  To assist in achieving this objective the Inspectorate has adopted a “Recovery Plan” for cases in England.  It is based upon the best information we have about our resources and the anticipated demands which will be placed on them during the remainder of the year.

Written representations

The Inspectorate is currently meeting  - and often exceeding - Ministerial targets for written representation appeals, but cannot sacrifice performance as a means of meeting targets on hearings and inquiries. For this reason, the recovery plan monitors the number of cases waiting for a site visit.

Hearings and inquiries

The graphs below measure the gap between cases ‘start date’ and the event date.  We have counted (and assumed) the numbers of cases with start dates and calculated on the basis of expected/target rates of work, when these events will take place.  Once we reach the point where events are taking place within 6 months of the start date, we reach the “tipping point” from which there should be sufficient time for decisions to be issued in target.

Chart showing the SOS targets

Chart showing the closing date

The following is a summary of how our recovery will impact upon the time elapsed between start dates and events.

These dates/timings can be regarded as our expected performance in general terms (there will always be exceptions) but note that in the case of hearings and inquiries, the information relates to our first offer date (which the parties have a right to decline).

Written representation cases

Start dates

Event

Any

between 12-14 weeks of start date.

 

Hearings
10+ Housing cases

Start dates

First offer date

Any

Within 20 weeks of start date. 

General section 78 cases

Start dates

First offer date

February, March or April 06

November 06

May 06

December 06

June or July 06

January 07

August to November 06

between 22 to 26 weeks from start date


Local inquiries
10+ Housing cases

Start dates

First offer date

Any

Within 20 weeks of start date. 


SoS cases (including called in, recovered and CPOs)

Start dates

First offer date

Any

Within 22 weeks of start date. 

General section 78 cases  (for inquiries with a duration of less than a week)

Start dates

First offer date

October 05 to January 06

October 06

February 06 to April 06

November 06

May 06 to July 06

December 06 or January 07

August 06 to October 06

February 07

November onwards

approximately 22 weeks from start date

Phil Hammond
Operations Manager, Chartroom

>> back to newsletter